Prevoius Weekly Reports

   07.11.2009
    

ROB to Athani

Work Planned upto 14/11/2009 Completed/Progress Delay
Kerb concreting Completed  
Handrail & Footpath slab In progress  
RE wall works Not started  
Excavation for bellmouth on Shornur side In progress
Delay 20 days due to shifting
of Utilities
 