Prevoius Weekly Reports

   weekly progress 12.8.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 12.08.2011 
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week  
1 Pile towards NH side 26 26 0 0 1 1 0 0
2 Pile towards Puliyanam side 18 6 12 1 2 0 2 4

 

Date 06.07.2011 08.08.2011 09.08.2011 10.08.2011 11.08.2011 12.08.2011
Climate pleasant cloudy rainy sunny rainy pleasant
No.of labours 42 39 37 42 39 39
availability of material            
materials Required Available        
Fine aggregate(M3) 10 15        
Coarse aggregate(M3) 20 30        
Cement(BAG) 220 600        
Steel(TONN) 5 22        
 
Back
 
    
PILE CAP P8 EXCAVATION(08.08.11).

    
    
PILE CAP P9 RFT WORK(09.08.11)

    
    
RFT FOR DIRT WALL & PEDASTAL(10.08.11).

    
    
RFT FOR DIRT WALL & PEDASTAL(10.08.11).

    
 
    
STABILIZING THE DIVERTION ROAD(11.08.11).

      
 

 

 

 

 

 

 

 