Revised Progress Report For Mulankunnathukavu ROB for the week ending on 12-8-2011 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
|
|
|
Completed |
|
|
|
2 |
PILE M.C SIDE |
36 |
36 |
|
|
|
Completed |
|
|
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
6 |
PIER M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
9 |
RE/R WALL SHORNUR SIDE |
100% |
35 |
65% |
0 |
5.00% |
5.00% |
42.00% |
10.00% |
0 |
Reinforcement work for the raft for a distance of 10metre,earthwork excavation for a distance of 25metre |
10 |
RE/R WALL M.C SIDE |
100% |
9 |
91% |
0 |
0.00% |
0.00% |
2.00% |
0.00% |
0 |
|
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
deshuttering of the slab ,beam sides of the span P1-P2 progressing fast |
12 |
BEAM/SLAB M.C SIDE |
12 |
7 |
5 |
0 |
1 |
1 |
3 |
1 |
27 DAYS |
beam reinforcement of the span P6-P5 in progress.deshuttering of the span P7-P6 in progress.Dirt wall concreting at AP2 to be done today. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
3 |
97% |
0 |
1.00% |
0.00% |
0.00% |
0.00% |
0 days |
kerb concreting of the span P1-P2 complete. |
14 |
HR/FP/KERB M.C SIDE |
100% |
9 |
91% |
0 |
0.00% |
10.00% |
0.00% |
1.00% |
|
kerb concreting of the span P7-P6 completed.HANDRAIL POST FIXING AND CONCRETING COMPLETED FOR AP2-P13 AND P12-P13. |
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
6/8/2011 |
7/8/2011 |
8/8/2011 |
9/8/2011 |
|
10/8/2011 |
11/8/2011 |
12/8/2011 |
|
|
|
Nof labours |
40 |
38 |
43 |
36 |
|
47 |
45 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
|
|
|
|
|
|
|
|
|
|
|
|
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Fine aggregate {cft} |
650 |
800 |
|
|
|
|
|
|
|
|
|
Cement(bag) |
200 |
500 |
no material shortage at site |
|
|
|
|
|
|
|
|
Steel inT |
11 |
14 |
|
|
|
|
|
|
|
|
|
Coarse Aggreagate (cft) |
430 |
630 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
|
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
COMPLETED |
|
|
|
|
|
|
|
|
|
|
KSEB |
COMPLETED |
|
|
|
|
|
|
|
|
|
|
KWA |
COMPLETED |
|
|
|
|
|
|
|
|
|
|
Others |
COMPLETED |
|
|
TOTAL NUMBER OF HANDRAILS CASTED IS 76 upto this date |
|
|
|
|
|
|