Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886780
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 12.8.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 12-8-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 5.00% 5.00% 42.00% 10.00% 0 Reinforcement work for the raft for a distance of 10metre,earthwork excavation for a distance of 25metre
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 0  
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0 deshuttering of the slab ,beam sides of the span P1-P2 progressing fast
12 BEAM/SLAB M.C SIDE 12 7 5 0 1 1 3 1 27 DAYS beam reinforcement of the span P6-P5 in progress.deshuttering of the span P7-P6 in progress.Dirt wall concreting at AP2 to be done today.
13 HR/FP/KERB SHORNUR  SIDE 100% 3 97% 0 1.00% 0.00% 0.00% 0.00% 0 days kerb concreting of the span P1-P2 complete.
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 0.00% 10.00% 0.00% 1.00%   kerb concreting of the span P7-P6 completed.HANDRAIL POST FIXING AND CONCRETING COMPLETED FOR AP2-P13 AND P12-P13.
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 6/8/2011 7/8/2011 8/8/2011 9/8/2011   10/8/2011 11/8/2011 12/8/2011    
  Nof labours 40 38 43 36   47 45      
                       
  Material Stocking Status                    
    Required Available Remarks              
  Fine aggregate {cft} 650 800                
  Cement(bag) 200 500 no material shortage at site              
  Steel inT 11 14                
  Coarse Aggreagate (cft) 430 630                
                       
  Utility shifting                    
  Utilities to be shifted   Remarks                
  BSNL COMPLETED                  
  KSEB COMPLETED                  
  KWA COMPLETED                  
  Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date            
 
Back
 
    
HANDRAIL FIXING AND CONCRETING ATAP-AP2 -PI3

    
    
EXPANSION JOINT CONCRETING AT P12

    
    
DIRT WALL CONCRETING 2ND STAGE AT AP2

    
    
DECK SLAB CONCRETING P7-P6.

    
 
    
CHANNEL LAYING FOR BOTTOM SHUTTERING AT P6-P5

      
 

 

 

 

 

 

 

 

Untitled Document