Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888240
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 12.8.2011
    

 

Progress Report For Palakkad Sultanpet ROB for the week ending on12-08-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PCC for RAFT MOYAN SIDE 1 0 1 0 0 0 0 1    
2 PCC for RAFT PALAKKAD SCHOOL SIDE 3 2 1 1 1 0 0 0    
3 RAFT PALAKKAD SIDE 1 1 0 0 0 0 0 0    
4 RAFT MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
5 PIER PALAKKAD SIDE 1 1 0 0 0 0 0 0    
6 PIER MOYAN SCHOOL SIDE 3 3 2 0 0 0 0 0    
7 PIER CAP PALAKKAD SIDE 1 1 0 0 0 0 0 0    
8 PIER CAP MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0    
9 RE/R WALL PALAKKAD  SIDE 100% 61% 39% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL MOYAN SCHOOL SIDE 100% 40% 60% 0 0.00% 5.00% 0.00% 0.00%    
11 BEAM/SLAB  Staging Palakad  SIDE 2 1 1 0 0 0 0 1    
12 BEAM/SLAB  Bar bending and Fixing Palakad  SIDE 2 1 1 0 0 0 0 1    
13 BEAM/SLAB  Shuttering  and Concreting Palakad SIDE 2 1 1 0 0 0 0 o    
14 BEAM/SLAB  Staging Moyan schoolSIDE 4 4 0 0 0 0 0 1    
15 BEAM/SLAB  Bar bending and Fixing Moyan school SIDE 5 5 0 0 0 0 0 1    
16 BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE 5 5 0 0 0 0 0 1    RP6-RP7-RP8 (Y Portion) deck slab casting completed.
17 BEAM/SLAB PALAKKAD  SIDE 3 0 3 0 0 0 0 0    
18 BEAM/SLAB MOYAN SCHOOL SIDE 5 5 0 0 0 0 1 1    
19 BEAM/SLAB RAILWAY SPAN 7 0 7 0 0 0 1 0    
20 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
23 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
  Note: Progress review done based on the revised Program (rev-01)            
                       
  ROB Sulthanpet, Palakkad                    
  Date Barbenders Mechanics/Electricains Helpers Ret. Wall work            
  8/6/2011 4 7 16 15            
  8/7/2011 4 5 10 10            
  8/8/2011 4 7 16 15            
  8/9/2011 4 7 16 15            
  8/10/2011 10 7 16 18            
  8/11/2011 10 7 16 18            
  8/12/2011 10 7 16 18            
                       
                       
  Material Stocking Status                
    Required Available                
  Fine aggregate {m³} 8 40                
  Cement(bag) 400 450                
  Steel in T 8 85                
  Coarse aggregate (m3)  10  16                
 
Back
 
    
VETENARY HOPSITAL GATE WORK

    
    
RET WALL EXACAVTION

    
    
DESHUTTERING OF RP6-RP7-RP8

    
    
CONCRETING OF RET WALL RAFT

    
 
    
CASTING OF RET WALL

    
    
BARBENDING OF RET WALL RAFT

      
 

 

 

 

 

 

 

 

Untitled Document