Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887888
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 12.8.2011
    

 

Sl

No

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

.

2

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

 

3

Pier cap

2

1

1

45

 0

 0

 0

 0

 0

 Concretig  to be done today

 

 

4

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

 

5

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

 

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

 

7

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

8

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of 15 metres.Handrailposts  concreted for a distance of 25 metres

 

Nil

20m handrail fixing

25m handrail fixing

       0

 

Balance portion of kerband handrails..

 

 

9

Friction slab  approach portion(N.H side

200m

 

friction slab  completed upto60 m total.Nowork in the last week.

 

 

 

 

      7

 

 

 

 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

12

21

Remarks

 

Fine Aggreagate(m3)

 15

 11

 .

 

Cement(bag)

 31

 75

 

 

Steel(MT)

 6

 15

 

 

 RE blocks

 2150 available at site

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

  

 
Back
 
    
CONCRETING OF FOOTPATH SLAB IN PULIKKAKADAVU SIDE(10.8.2011).

    
    
CONSTRUCTION OF TOLL BOOTH AT PULIKKAKADAVUAPPROACH PORTION(12.8.2011).

    
    
HAND RAIL FIXING AND CONCRETING AT APPROACH SIDE OF N.H(9.8.2011).

    
    
HANDRAIL POSTS DESHUTTERING(8.8.2011).

    
 
    
PIERCAP P2 REINFORCEMENT AND SHUTTERING WORK(11.8.2011).

    
    
PIERCAP P2 SHUTTERING WORK(8.8.2011).

      
 

 

 

 

 

 

 

 

Untitled Document