Sl
No
|
Activity –which can be completed without caution
Description
|
Total Quantity
|
Cumulative progress up to this week
(1)
|
Balance work
(2)
|
Cumulative delay in weeks after
Spplagmnt
(3)
|
Work planned during the week
(4)
|
Actual work done during the last week
(5)
|
Short fall in the last week
(6)
|
Work
Planned for next week
(7)
|
No of days remaining for completion as per the weekly plan
|
Remarks
|
8
|
Kerb/handrail (approach portion)N.H side
|
200m
|
Inner kerbconcreting complete for a distance of 15 metres.Handrailposts concreted for a distance of 25 metres
|
|
Nil
|
20m handrail fixing
|
25m handrail fixing
|
0
|
Balance portion of kerband handrails..
|
|
|