   weekly progress 12.8.2011
    

 

 Progress Report For Ponnurunni ROB for the week ending on 11-08-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 11.08.11 Balance  work up to 11.08.11 Cumulative delay in Qty up to11.08.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS. RAILWAY SIGNAL AND RAIL TEL CABLES TO SHIFTED FOR TAKING UP WORKS AT RP1.
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 "      "
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      " A2, P15, P14, P13,  P12,  P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "  
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 0 8 0 0 0 0 2    
14 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
15 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
16 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
17 RE WALL PANEL 370 334 36 2 35 24 13 12 5  

 

 

Labour Report              
               
Date 05.08.11 06.08.11 07.08.11 8.0811 09.08.11 10.08.11 11.08.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate rainy sunny sunny sunny sunny rainy rainy
No.of labours 22 20 0 20 20.5 21 21
               
Availability of Material               
Materials Required for week ending on 11.08.11 Available as on 05.08.2011          
Fine aggregate(M3) Ready Mix Concrete          
Coarse aggregate(M3)          
Cement(BAG)          
Steel(TONN) 1.6 29.8          
 
Back
 
    
SLUMP TEST(10.8.2011)

    
    
PIER CAP P15 SHUTTERING(11.8.2011).

    
    
PIER P10 CONCRETING(9.8.2011)

    
    
PIER P10 SHUTTERING(8.8.2011).

    
 
    
PANEL CASTING(6.8.2011)

    
    
PIER P11 CONCRETING(5.8.2011)

      
 

 

 

 

 

 

 

 