ROB at Athani
Work Planned upto 20.03.2010 |
Completed/Progress |
Remarks |
RE wall works Medical College side |
No work |
|
Fixing of panels 60m length |
3 layer completed |
Delay due to shortage of earth for filling |
Shornur side |
|
|
Hand rail for RE wall |
In progress |
|
Drain excavation |
In progress |
|
|
|