   weekly progress as on 5.8.2011
    

 

Progress Report For Kainatty ROB for the week ending on 29-07-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 4 2 2 2 0 2 2    
4 PILE CAP  NADAPURAM SIDE 9 7 2 2 2 0 2 2    
5 PIER KAINATTY  SIDE 6 4 2 3 3 0 2 2    
6 PIER NADAPURAM SIDE 9 7.5 1.5 3.8 1.5 0 1.5 1.5    
7 PIER CAP KAINATTY  SIDE 6 4 2 6 2 0 2 2    
8 PIER CAP NADAPURAM SIDE 9 6 3 5 3 0 3 3    
11 RE/R WALL KAINATTY  SIDE 100% 0% 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 23% 77% 0 0.00% 2.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 3 3 3 1 0 3 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 2 4 3 1 0 4 1    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 2 4 3 0 0 4 1    
15 BEAM/SLAB  Staging Nadapuram side 9 2 7 3 0 1 7 0   bottom shuttering work in progress
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 2 7 3 0 0 7 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 1 8 3 0 *0 8 0   *slab reinforcement done 15%
18 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 0 0 0    
19 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
                       
  Note: Progress review done based on the revised Program (rev-01)            
                       
                       
  Availbility of Men                     
  Date   30-7-2011 31-7-2011 1/8/2011 2/8/2011 3/8/2011 4/8/2011 5/8/2011    
  Nof labours   60 60 60 60 60 60 60    
                       
  Material Stocking Status Required Available Remarks              
                       
  Fine Aggreagate(m3) 12 6                
  Cement(bag) 150 650                
  Steel(MT) 10 30                
  Coarse Aggreagate (m3) 15 15                
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL in progress                  
  KSEB shifted                  
  KWA shifted                  
  Others shifted                  
 