   weekly progress 5/8/2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 05-8-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE SHORNUR  SIDE 9 9       Completed    
2 PILE M.C SIDE 36 36       Completed      
3 PILE CAP SHORNUR SIDE 3 3       Completed      
4 PILE CAP  M.C SIDE 12 12       Completed      
5 PIER SHORNUR  SIDE 3 3       Completed      
6 PIER M.C SIDE 12 12       Completed      
7 PIER CAP SHORNUR  SIDE 3 3       Completed      
8 PIER CAP M.C SIDE 12 12       Completed      
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 10.00% 0.00% 42.00% 5.00% 0
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 0
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0
12 BEAM/SLAB M.C SIDE 12 7 5 0 1 0 4 1 34 DAYS
13 HR/FP/KERB SHORNUR  SIDE 100% 3 97% 0 1.00% 5.00% 0.00% 0.00% 0 days
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 0.00% 0.00% 0.00% 1.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Deck Slab                  
17 Utility shifting                  
                     
                     
                     
  Availbility of Men                   
  Date 30-7-2011 31-7-2011 1/8/2011 2/8/2011 3/8/2011 4/8/2011 5/8/2011    
  Nof labours 40 38 43 36 43 47 45    
                     
  Material Stocking Status                  
    Required Available Remarks            
  Fine aggregate {cft} 650 800              
  Cement(bag) 200 500 no material shortage at site            
  Steel inT 11 16              
  Coarse Aggreagate (cft) 430 800              
                     
  Utility shifting                  
  Utilities to be shifted   Remarks              
  BSNL COMPLETED                
  KSEB COMPLETED                
  KWA COMPLETED                
  Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date       IS 240 upto today today
 
Back
 
    
STAGING WORKS AT P6-P5

    
    
SLAB TOP REINFORCEMENT LAYING AT P6-P7

    
    
SLAB TOP REINFORCEMENT LAYING AT P6-P7

    
    
SLAB TOP REINFORCEMENT LAYING AT P6-P7

    
 
    
SLAB REINFORCEMENT AT P6-P7

    
    
PCC LAYING AT P5-P4

    
    
LOADING OF MATERIALS FOR GIRDER CONCRETE OF P6-P7

    
 
    
END DIAPHRAGM CONCRETING AT P6-P7

    
    
EXPANSION JOINT WORK AT P13

    
    
BEAM SHUTTERING WORK AT P6-P7

    
 
 
 

 

 

 

 

 

 

 