Prevoius Weekly Reports
|
03.04.2010 |
| |
ROB at Athani
|
Work Planned upto 03.04.2010 |
Completed/Progress |
Remarks |
|
RE wall works Medical College side |
No work |
|
|
Fixing of panels 60m length |
3 layer completed |
|
|
Shornur side |
|
|
|
Hand rail for RE wall |
In progress |
|
|
Drain excavation |
Completed |
|
|
RCC work for drain |
In progress |
|
|
| |