Untitled Document
Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
7886944
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Prevoius Weekly Reports
weekly progress 5.8.2011
Pile rig mobilisation
In progress
Site level survey
In progress
Cube test
In progress
filling work in piling location
In progress
Back
PILING RIG 2 MOBILISED
PILING RIG 1 MOBILISED.
MIXING OF AGGREGATES & CEMENT FOR TAKING CUBES.
CUBES CASTED.JPG
BENTONITE TANK.JPG