   weekly progress 5.8.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 05.08.2011   
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 1 1 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 6 12 1 2 1 1 2 ROAD DIVERSION  DELAYED DUE HEAVY RAIN

 

Date 30.07.2011 01.08.2011 02.08.2011 03.08.2011 04.08.2011 05.08.2011
Climate rainy moody rainy rainy pleasant rainy
No.of labours 35 35 37 37 40 35

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

 

 
Back
 
    
PILE CAP A2 - STUB COLUMN REINFORCEMENT WORK (04.08.11).

    
    
PILE CAP P9 REINFORCEMENT WORK (02.08.11).

    
    
PILE CAP P8 EXCAVATION(5.8.2011)

    
    
PILE CAP P9 REINFORCEMENT WORK (05.08.11)

    
 
    
PILE P2C CONCRETING (03.08.11).

    
    
PILE P6D CONCRETING (02.08.11)

      
 

 

 

 

 

 

 

 