   weekly progress 5.8.2011
    

 

Progress Report For Ponnurunni ROB for the week ending on 04-08-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 04.08.11 Balance  work up to 04.08.11 Cumulative delay in Qty up to 04.08.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 KWA  LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS. RAILWAY SIGNAL AND RAIL TEL CABLES TO SHIFTED FOR TAKING UP WORKS AT RP1.
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 A2, P15, P14, P13,  P12,  P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0  
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 railway signal cable to be shifted
9 PIER Palarivattom side(Approach portion) 8 6 2 0 3 3 0 2 A2, P15, P14, P13,  P12,  P11 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0  
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 railway signal cable to be shifted
13 RE WALL PANEL 370 310 60 2 35 33 4 35  

 

Date 29.7.2011 30.7.2011 31.7.2011 1.8.2011 2.8.11 3.8.2011 4.8.2011
Day Fri Sat Sun Mon Tue Wed Thurs
Climate sunny sunny sunny Rain sunny sunny sunny
No.of labours 16 15.5 5.5 17 21 23 22
Materials Required for week ending on 04.08.11 Available as on 4.8.2011
Fine aggregate(M3) Ready Mix Concrete
Coarse aggregate(M3)
Cement(BAG)
Steel(TONN) 5 27.5 
 
Back
 
    
CUBE TEST(3.8.2011).

    
    
BOOM PUMP AT SITE FOR PIER P10 CONCRETING(30.7.2011).

    
    
COMPLETED PORTION(29.7.2011).

    
    
PIER P10 CONCRETING WITH BOOM PUMP(30.7.2011).

    
 
    
PIER P11 CONCRETING(2.8.2011)

    
    
SLUMP TEST(29.7.2011).

      
 

 

 

 

 

 

 

 