   weekly progress as on 29.7.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 29-7-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 10.00% 0.00% 42.00% 5.00% 4 days  
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 4 days  
11 BEAM/SLAB SHORNUR  SIDE 3 1 2 0 1 1 0 0 0 beam and deck slab concreting of span P1-P2 of the shornur side has been completed.
12 BEAM/SLAB M.C SIDE 12 7 5 0 0 0 5 1 41 days  girder reinforcement of the span P6-P7 is in progress.Levelling and laying of PCC completed for the span P6-P5 and P5-P4.Pedestal concreting of P5 over.Staging work of P6-P5 will commence today
13 HR/FP/KERB SHORNUR  SIDE 100% 3 97% 0 0.00% 1.00% 0.00% 0.00% 0 days  
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 2.00% 3.00% 0.00% 1.00%   kerb concreting of P8-P9 completed on both sides.Total number of handrails casted is 200 till date
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    

 

Availbility of Men               
Date 23-7-2011 24-7-2011 25-7-2011 26-7-2011 27-7-2011 28-7-2011 29-7-2011
Nof labours 43 45 57 59 60 60 59

 

Material Stocking Status        
  Required Available Remarks  
Fine aggregate {cft} 650 300    
Cement(bag) 200 950 stock will be replendished soon  
Steel inT 11 20    
Coarse Aggreagate (cft) 430 300    

 

 

Utility shifting        
Utilities to be shifted   Remarks    
BSNL COMPLETED      
KSEB COMPLETED      
KWA COMPLETED      
Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date
 
Back
 
    
SLAB REINFORCENMENT OF P1-P2 25-7-11

    
    
SLAB REINFORCEMENT-SPAN P1-P2 23.7.11

    
    
KERB CONCRETING OF SPAN P8-P9 23711

    
    
GIRDER CONCRETING OF SPAN P1-P2 27-7-11

    
 
    
BOTTOM SHUTTER SETTING OF SPANP6-P726-7-11.

    
    
BEAM REINFOREMENT IN PROGRESS AT P6-P7(29.7.2011).

      
 

 

 

 

 

 

 

 