   weekly progress 29.7.2011
    

 

SlNo

Activity -Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

34

66

30

RR work

RR work

 

0

0

 5

.

3

Approach

 Span

 

5

 

4

1

36

-

-

-

-

 

 

4

Pier cap

4

1

3

39

 0

 0

 0

 0

 4

PiercapP1 concreting planned for the next week

5

Pile (Rly)pulikakadavuside

9

4

 

5

58

 0

 0

0

 

6

Pile (Rly)Nhside

9

4

5

58

0

0

0

0

0

 

6

Piers (Rly)

 

4

2

2

49

 0

 0

 0

 0

 

3rdlift concreting of the pier P1  at N.H side  completed

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90%

 

0

 

 

 

 

 

 

 

10

GIRDER

(LAND SPAN)

P2-P3 span

3

3

 

 

 

 

 

 

 

1ststage stressing over

11

P2-P3 span

 

 

 

 

Kerbconcreting of P2-P3

Kerbconcreting of both outer kerbscompleted

 

 

Inner kerbconcreting of P2-P3

 

 

12

Diaphramwall

(P2-P3)

 

 

 

 

 

 

 

 

 

 

 

Re wall ,Kerb and hand rail towards Pulikkakadavuside completed

 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

12

23

Remarks

 

Fine Aggreagate(m3)

 10

 25

 .

 

Cement(bag)

 22

 32

 

 

Steel(MT)

 6

 11

 

 

 RE blocks

 2150 available at site

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 i

 

  

 
Back
 
    
ARRANGEMENT FOR STRESSING WORK AT P2-P3(26.7.2011).

    
    
KERB SHUTTERING OF SPAN N.H APPROACH(26.7.2011)

    
    
FRICTION SLAB AND KERB REINFORCEMENT OF N.H APPROACH(25.7.2011).

    
    
SPAN P2-P3 AFTER DESHUTTERING(25.7.2011).

    
 
    
STRESSING WORK AT P2-P3(26.7.2011)

    
    
CONCRETING OF SHOE PORTION FOR HANDRAILS AT N.H SIDE(28.7.2011)

      
 

 

 

 

 

 

 

 