   weekly progress 29.7.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 29.7.2011   
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 25 1 1 2 1 1 1  
2 Pile towards Puliyanam side 18 5 13 1 2 1 1 2   

 

Date 23.07.2011 25.07.2011 26.07.2011 27.07.2011 28.07.2011 29.04.2011
Climate rainy moody pleasant pleasant moody moody
No.of labours 35 39 44 33 35 33 

 

availability of material    
materials Required Available
Fine aggregate(M3) 8 13
Coarse aggregate(M3) 20 30
Cement(BAG) 250 430
Steel(TONN) 4 20 
 
Back
 
    
RFT WORK FOR PILECAP A2.(26.7.2011)

    
    
PILE P6.C ( 25.07.11)

    
    
PILE LOAD TEST ON P7(20-07-11).

    
    
PILE LOAD TEST (21-07-11).

    
 
 
 

 

 

 

 

 

 

 