   Weekly Progress Report as on 29/07/2011
    

 

Progress Report For Kainatty ROB for the week ending on 29-07-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 4 2 2 2 0 2 2    
4 PILE CAP  NADAPURAM SIDE 9 7 2 2 2 0 2 2    
5 PIER KAINATTY  SIDE 6 4 2 3 3 0 2 2    
6 PIER NADAPURAM SIDE 9 7.5 1.5 3.8 1.5 0 1.5 1.5    
7 PIER CAP KAINATTY  SIDE 6 4 2 6 2 0 2 2    
8 PIER CAP NADAPURAM SIDE 9 6 3 5 3 0 3 3    
11 RE/R WALL KAINATTY  SIDE 100% 0% 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 23% 77% 0 0.00% 2.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 3 3 3 1 0 3 1    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 2 4 3 1 0 4 1    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 2 4 3 0 0 4 1    
15 BEAM/SLAB  Staging Nadapuram side 9 2 7 3 0 0 7 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 1.6 7.4 3 0 0.4 7.4 1    
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 1 8 3 0 *0 8 0   *girder concrete completed
18 BEAM/SLAB KAINATTY  SIDE 6 0 6 0 0 0 0 0    
19 BEAM/SLAB NADAPURAM SIDE 9 0 9 0 0 0 0 0    
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
 
Back
 
    
P12-P13 DESHUTTERING

    
    
HANDRAIL STEEL WORK (28.07.2011)

    
    
P9-P10 SHUTTERING WORKS (28.07.2011)

    
    
DIVERSION ROAD(REPAIRED) (28.07.2011)

    
 
    
RE WALL PANEL CASTING (26.07.2011)

    
    
STAGING P2-P3 (26.07.2011)

      
 

 

 

 

 

 

 

 