Si No
Activity Description
Total Quantity
Cumulative progress uptolast week
Balance work up to last week
Cumulative delay in Qty up to this week
Work planned during the week
Actual work done during the week
Work Planned for next week
Remarks
1
RE/R WALL PALAKKAD SIDE
100%
62%
38%
0
2.00%
2
RE/R WALL MOYAN SCHOOL SIDE
31%
69%
3.00%
3
BEAM/SLAB Staging PALAKKAD SIDE
4
BEAM/SLAB Bar bending and Fixing PALAKKAD SIDE
5
BEAM/SLAB Bar Shuttering And Concreting PALAKKAD SIDE
6
BEAM/SLAB Staging MOYAN SCHOOL SIDE
7
BEAM/SLAB Bar bending And Fixing MOYAN SCHOOL SIDE
8
BEAM/SLAB Shuttering and Concreting MOYAN SCHOOL SIDE
9
BEAM/SLAB RAILWAY SPAN
10
HR/FP/KERB CALICUT SIDE
0.00%
11
HR/FP/KERB NH SIDE
12
HR/FP/KERB RAILWAY SPAN
13
BC/PAINTING
Note: Progress review done based on the revised Program (rev-01)