   Report as on 22.07.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 22-7-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 10.00% 2.00% 32.00% 10.00% 11 days  
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 11 days  
11 BEAM/SLAB SHORNUR  SIDE 3 1 2 0 0 0 0 1 0 beam reinforcement and beam shuttering work in progress at P1-P2.Slab bottom shuttering work will start today
12 BEAM/SLAB M.C SIDE 12 7 5 0 0 0 5 0 48 days  staging works of location P6-P7 in progress at a slow pace.
13 HR/FP/KERB SHORNUR  SIDE 100% 3 97% 0 0.00% 1.00% 0.00% 0.00% 0 days  
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 2.00% 3.00% 0.00% 1.00%   kerb concreting of P8-P9,P11-P12 completed.Total number of handrails casted is 175 till date
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                     

 

Availbility of Men                   
Date 16-7-2011 18-7-2011 19-7-2011 20-7-2011   21-7-2011 22-7-2011    
Nof labours 21 23 22 25   25 34     

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 650 340      
Cement(bag) 200 950 stock will be replendished soon    
Steel inT 11 26      
Coarse Aggreagate (cft) 430 330      

 

Utility shifting                  
Utilities to be shifted   Remarks              
BSNL COMPLETED                
KSEB COMPLETED                
KWA COMPLETED                
Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date       IS 175 upto today today 
 
Back
 
    
KERB CONCRETING AT P11-P12 22.07.2011

    
    
LIFTING OF SHUTTERING MATERIALS AT P1-P2 16.07.2011

    
    
BEAM SHUTTERING AND REINFORCEMENT AT P1-P2 18.07.2011

    
    
STAGING WORK AT P6-P7 19.07.2011

    
 
    
BEAM SHUTTERING COMPLETED ON ONE SIDE AT P1-P2 20.07.2011

    
    
KERB CONCRETING 20.07.2011

    
    
BEAM SHUTTERING WORK NEARING COMPLETION AT P1-P2 21.07.2011

    
 
 
 

 

 

 

 

 

 

 