Work Planned upto 22.05.2010
|
Completed/Progress |
Remarks |
P3-P4 Span |
|
Road Blocked for P3-P4 span work. |
Stressing and Grouting |
Completed |
|
Concreting of Diaphram beam |
Completed |
|
Shuttering and reinforcement work for slab |
In progress |
|
Approval of GAD by railways (Railway Portion) |
Approved |
Approved on 1/5/10 |
Preparation of Design and Drawing |
In progress |
|
Box culvert works (under pass) - Raft concreting |
Completed |
|