ROB at Koratty

PROGRESS AS ON 22.05.2010

 

    
   Work Planned upto 22.05.2010 
Completed/Progress  Remarks
P3-P4 Span    Road Blocked for P3-P4 span work.
Stressing and Grouting  Completed   
Concreting of Diaphram beam  Completed   
Shuttering and reinforcement work for slab In progress  
Approval of GAD by railways (Railway Portion) Approved Approved on 1/5/10
Preparation of Design and Drawing  In progress  
Box culvert works (under pass) - Raft concreting Completed   


 

 