SlNo
|
Activity –which can be completed without caution
Description
|
Total Quantity
|
Cumulative progress up to this week
(1)
|
Balance work
(2)
|
Cumulative delay in weeks after
Spplagmnt
(3)
|
Cumulative progress uptothis week
(4)
|
Actual work done during the last week
(5)
|
Short fall in the last week
(6)
|
Work
Planned for next week
(7)
|
No of days remaining for completion as per the weekly plan
|
remarks
|
1O
|
Kerb/handrail (approach portion)N.H side
|
200m
|
Kerbcompleted uptoa cumulative length of 20 metres.
|
|
nil
|
Cumulative length 20 metreconcreting completed.
|
|
0
|
|
|
|
12
|
Friction slab approach portion(N.H side
|
200m
|
friction slab completed upto55 metrestotal
|
|
|
Friction slab concrete completed for a length of 55 metres
|
25 metresconcreting completed due to rain
|
|
Friction slab concrete planned for 6 metres
|
|
less scope of work due to incompletion of re wall
|