Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887977
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 22.7.2011
    

 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Cumulative progress uptothis week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

remarks

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

.

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

 

4

Pier cap

2

1

3

43

 0

 0

 0

 0

 0

 pier cap cannot be planned for next week due to change in design

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

 

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

 

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Kerbcompleted uptoa cumulative length of 20 metres.

 

nil

Cumulative length 20 metreconcreting completed.

 

       0

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

friction slab  completed upto55 metrestotal

 

 

Friction slab concrete completed for a length of 55 metres

25 metresconcreting completed due to rain

   

Friction slab concrete planned for 6 metres

 

less scope of work due to incompletion of re wall

 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

12

18

Remarks

 

Fine Aggreagate(m3)

 15

 25

 .

 

Cement(bag)

 15

 20

 

 

Steel(MT)

 6

 20

 

 

 RE blocks

 2150 available at site

 

 

  

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 i

 

  

 

DATE

16-07-2011

18-7-2011

19-7-2011

20-7-2011

21-7-2011

22-7-2011

Weather

cloudy

Rainy

Rainy

cloudy

rainy

rainy

No of labours 21 21 20 20 21 21

 

 
Back
 
    
FRICTION SLAB AT N.H APPROACH AFTER DESHUTTERING(17.7.2011).

    
    
ELASTOMERIC PAINTING ON THE SLAB BOTTOM OF P2-P3(17.7.2011).

    
    
CONCRETING OF FRICTION SLAB(20.7.2011)

    
    
FRICTION SLAB AND KERB REINFORCEMENT AT N.H APPROACH( 18.7.2011).

    
 
    
FRICTION SLAB SHUTTERIING AND REINFORCEMENT AT N.H APPROACH(21.7.2011).

    
    
CONCRETING OF FRICTION SLAB AT N.H SIDE APPROACH(20.7.2011).

      
 

 

 

 

 

 

 

 

Untitled Document