Untitled Document
Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
8053865
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Prevoius Weekly Reports
Weekly Progress Report as on 22/07/2011
ROB at Cheruvathur
Pile concreting
in progress
Done 21nos. Balance can be done only after getting the land
Pile load testing arrangement P8 a
in progress
after getting the land.
AP2,P15,P13 consolidation and marking
completed
Building demolishen in Padanna
In progress
KSEB utility shifting near AP2
Completed
BSNL cable shifting near P10
In progress
Back
CONCRETING ON AP2 C (17.07.2011)
BORING AT AP2 A (19.07.2011)
REINFORCEMENT ERECTION ON AP2 A (19.07.2011)
TREMIE PIPE ERECTION ON AP2 A (19.07.2011)
CONCRETING ON AP2 A (19.07.2011)
LOAD TESTING ARRANGEMENTS ON P8 (22.07.2011)