Revised Progress Report For Ponnurunni ROB for the week ending on 22-07-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto 217.11 |
Balance work up to 21.7.11 |
Cumulative delay in Qty up to 21.7.11 |
Work planned during the week |
Actual work done during the week |
delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE Palarivattom side(Approach portion) |
31 |
28 |
3 |
0 |
0 |
0 |
0 |
0 |
kwa line to be shifted |
KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS |
2 |
PILE Palarivattom side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
" " |
3 |
PILE vytilla side(Approach portion) |
42 |
0 |
42 |
0 |
0 |
0 |
0 |
0 |
" " |
4 |
PILE vytilla side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
" " |
5 |
PILE CAP Palarivattom side(Approach portion) |
8 |
7 |
1 |
1 |
1 |
1 |
0 |
0 |
" " |
A2, P15, P14, P13, P12, P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line. |
6 |
PILE CAP Palarivattomside(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
" " |
|
7 |
PILE CAP vytilla side(Approach portion) |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
" " |
|
8 |
PILE CAP vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
" " |
|
9 |
RE WALL PANEL |
370 |
247 |
123 |
0 |
35 |
28 |
7 |
35 |
19 |
|
|
Labour Report |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Date |
15.7.2011 |
16.7.2011 |
17.7.2011 |
18.7.2011 |
19.7.2011 |
20.7.2011 |
21.7.2011 |
|
|
|
|
Day |
Fri |
Sat |
Sun |
Mon |
Tue |
Wed |
Thurs |
|
|
|
|
Climate |
Rain |
Rain |
Rain |
Rain |
no work CITU strike |
Rain |
no work CITU strike |
|
|
|
|
No.of labours |
19 |
14 |
4 |
3 |
0 |
6 |
0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availability of Material |
|
|
|
|
|
|
|
|
|
|
|
Materials |
Required for week ending on 21.7.11 |
Available as on 15.7.2011 |
|
|
|
|
|
|
|
|
|
Fine aggregate(M3) |
Ready Mix Concrete |
|
|
|
|
|
|
|
|
|
Coarse aggregate(M3) |
|
|
|
|
|
|
|
|
|
Cement(BAG) |
|
|
|
|
|
|
|
|