Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053437
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 22.7.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 22-07-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 217.11 Balance  work up to 21.7.11 Cumulative delay in Qty up to 21.7.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted KWA & KSEB SERVICE LINES TO BE SHIFTED FOR RESUMING THE PILING WORKS
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 "      "
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      " A2, P15, P14, P13,  P12,  P11 & P10-- 8th Pilecap (P9) can be done only after shifting KWA line.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "  
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
9 RE WALL PANEL 370 247 123 0 35 28 7 35 19  
  Labour Report                    
                       
  Date 15.7.2011 16.7.2011 17.7.2011 18.7.2011 19.7.2011 20.7.2011 21.7.2011      
  Day Fri Sat Sun Mon Tue Wed Thurs      
  Climate Rain Rain Rain Rain no work CITU strike  Rain no work CITU strike      
  No.of labours 19 14 4 3 0 6 0      
                       
  Availability of Material                     
  Materials Required for week ending on 21.7.11 Available as on 15.7.2011                
  Fine aggregate(M3) Ready Mix Concrete                
  Coarse aggregate(M3)                
  Cement(BAG)                
 
Back
 
    
ABUTMENT PIER REINFORCEMENT (16.7.2011).

    
    
RE WALL PANEL CASTING(18.7.2011)

    
    
RE WALL PANEL CASTING(20.7.2011

    
    
RE WALL PANEL SHIFTING(20.7.2011).

    
 
    
SLUMP TEST (18.7.2011)

      
 

 

 

 

 

 

 

 

Untitled Document