ROB at Athani
Work Planned upto 24.04.2010 |
Completed/Progress |
Remarks
|
RE wall works Medical College side |
In progress |
Restarted on 12.4.10 |
Fixing of panels 60m length |
4 layer completed |
Delay due to shortage of earth for filling |
Shornur side |
|
|
Hand rail for RE wall |
In progress |
|
Drain excavation |
Completed |
|
RCC work for drain |
In progress |
|
|