   weekly progress 15.7.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 15.7.2011   
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 23 3        nil 2 1 1 1  
2 Pile towards Puliyanam side 18 3 15        nil 2 2 0 2   

 

Date 09.07.2011 11.07.2011 12.07.2011 13.07.2011 14.07.2011 15.07.2011
Climate pleasant pleasant heavy rain heavy rain rainy moody
No.of labours 39 39 35 35 35 39 

 

availability of material    
materials Required Available
Fine aggregate(M3) 4.5 10
Coarse aggregate(M3) 18 35
Cement(BAG) 175 320
Steel(TONN) 5 25 
 
Back
 
    
BORING FOR PILE P6(14.7.2011).

    
    
CONCRETING OF PILE P3D (08.07.2011).

    
    
PILE P6B BORING (11.07.2011).

    
    
ROAD SECTIONING WORK( 14.7.2011).

    
 
    
EXCAVATION FOR PILE CAP P9(12.7.2011).

    
    