Prevoius Weekly Reports

   Report as on15.07.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 15-7-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 35 65% 0 10.00% 2.00% 32.00% 10.00% 18 days RCC retaining wall concrete complete for  a distance of 1O METRES MORE.total 30 metres
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 18 days  
11 BEAM/SLAB SHORNUR  SIDE 3 1 2 0 0 0 0 1 3  days beam reinforcement of the span P1-P2 in progress.deshuttering of span AP1-P1 in progress
12 BEAM/SLAB M.C SIDE 12 7 5 0 0 0 5 0 55 days  staging works of location P6-P7 in progress .Pedestal concrete of location P6 completed.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 3.00% 0.00% 0 days kerb concreting of AP1-P1 completed
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 2.00% 0.00% 0.00% 0.00%   .Total number of handrails casted is 175 till date
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                     

 

Availbility of Men                   
Date 09-07-2011 11.7-2011 12-7-2011 13-7-2011   14-7-2011 15-7-2011    
Nof labours 58 58 57 58   0 23     

 

Material Stocking Status        
  Required Available Remarks  
Fine aggregate {cft} 650 450    
Cement(bag) 200 1000    
Steel inT 11 34    
Coarse Aggreagate (cft) 430 520     

 

Utility shifting                  
Utilities to be shifted   Remarks              
BSNL COMPLETED                
KSEB COMPLETED                
KWA COMPLETED                
Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date       IS 145 upto today today 
 
Back
 
    
BEAM REINFORCEMENT OF SPAN P1-P2 15.07.2011

    
    
KERB CONCRETING AT AP1-P1 13.07.2011

    
    
BEAM REINFORCEMENT AT P1-P2 12.07.2011

    
    
PCC LAYING FOR STAGING AT P6-P7 11.07.2011

    
 
    
DESHUTTERING OF SPAN P8-P9 11.07.2011

    
    
STAGING WORK AT P6-P7 09.07.2011

    
    
BOTTOM SHUTTER SETTING AT P1-P2 08.07.2011

    
 
 
 

 

 

 

 

 

 

 