SlNo
|
Activity –which can be completed without caution
Description
|
Total Quantity
|
Cumulative progress up to this week
(1)
|
Balance work
(2)
|
Cumulative delay in weeks after
Spplagmnt
(3)
|
Work planned during the week
(4)
|
Actual work done during the last week
(5)
|
Short fall in the last week
(6)
|
Work
Planned for next week
(7)
|
No of days remaining for completion as per the weekly plan
|
Remarks
|
12
|
Friction slab approach portion(N.H side
|
200m
|
friction slab completed upto28 m total
|
|
|
Friction slab concrtecompleted for a length of 10 metres
|
Only 3m concreting completed due to rain
|
7
|
Friction slab concrteplanned for 10 metres
|
|
|