Revised Progress Report For Ponnurunni ROB for the week ending on 15-07-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto 147.11 |
Balance work up to 14.7.11 |
Cumulative delay in Qty up to 14.7.11 |
Work planned during the week |
Actual work done during the week |
delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
1 |
PILE Palarivattom side(Approach portion) |
31 |
28 |
3 |
0 |
0 |
0 |
0 |
0 |
kwa line to be shifted |
2 |
PILE Palarivattom side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
" " |
3 |
PILE vytilla side(Approach portion) |
42 |
0 |
42 |
0 |
0 |
0 |
0 |
0 |
" " |
4 |
PILE vytilla side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
" " |
5 |
PILE CAP Palarivattom side(Approach portion) |
8 |
7 |
1 |
1 |
1 |
1 |
0 |
0 |
" " |
6 |
PILE CAP Palarivattomside(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
" " |
7 |
PILE CAP vytilla side(Approach portion) |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
" " |
8 |
PILE CAP vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
" " |
9 |
RE WALL PANEL |
370 |
219 |
151 |
0 |
42 |
37 |
5 |
35 |
26 |
|
|
|
|
|
|
|
|
|
|
|
|
Date |
8.7.2011 |
9.7.2011 |
10.7.2011 |
11.7.2011 |
12.7.2011 |
13.7.2011 |
14.7.2011 |
|
|
|
Day |
Fri |
Sat |
Sun |
Mon |
Tue |
Wed |
Thurs |
|
|
|
Climate |
Rain |
Rain |
Rain |
H. Rain (No work) |
Rain |
Rain |
H. Rain |
|
|
|
No.of labours |
18 |
18 |
2 |
3 |
13 |
12 |
13 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availability of Material |
|
|
|
|
|
|
|
|
|
|
Materials |
Required for week ending on 14.7.11 |
Available as on 7-7-2011 |
|
|
|
|
|
|
|
|
Fine aggregate(M3) |
Ready Mix Concrete |
|
|
|
|
|
|
|
|
Coarse aggregate(M3) |
|
|
|
|
|
|
|
|
Cement(BAG) |
|
|
|
|
|
|
|
|
Steel(TONN) |
2.5 |
19.08 |
|
|
|
|
|
|
|