Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053989
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 15.7.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 15-07-2011
Si No  Activity Description  Total Quantity Cumulative progress upto 147.11 Balance  work up to 14.7.11 Cumulative delay in Qty up to 14.7.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0 "      "
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0 "      "
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0 "      "
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 "      "
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0 "      "
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "
9 RE WALL PANEL 370 219 151 0 42 37 5 35 26
                     
  Date 8.7.2011 9.7.2011 10.7.2011 11.7.2011 12.7.2011 13.7.2011 14.7.2011    
  Day Fri Sat Sun Mon Tue Wed Thurs    
  Climate Rain Rain Rain H. Rain (No work) Rain  Rain H. Rain    
  No.of labours 18 18 2 3 13 12 13    
                     
  Availability of Material                   
  Materials Required for week ending on 14.7.11 Available as on 7-7-2011              
  Fine aggregate(M3) Ready Mix Concrete              
  Coarse aggregate(M3)              
  Cement(BAG)              
  Steel(TONN) 2.5 19.08              
 
Back
 
    
SLUMP CHECKING(14.7.2011).

    
    
SHUTTERING & REINFORCEMENT WORK - RE WALL PANEL(13.7.2011).

    
    
REFERENCE POINT MARKING FOR PIER P15(14.7.2011).

    
    
SHUTTERING & REINFORCEMENT WORK - RE WALL PANEL(13.7.2011).

    
 
    
REFERENCE POINT MARKING FOR PIER P15(14.7.2011)

    
    
RE WALL PANEL LIFTED TO STACKING YARD(8.7.2011).

    
    
PANEL CASTING(12.7.2011)

    
 
    
CONCRETE BEING PUMPED TO PILECAP P10(9.7.2011).

      
 

 

 

 

 

 

 

 

Untitled Document