Work Planned upto 29.5.2010 |
Completed / Progress |
Remarks |
P3-P4 Span |
|
Road Blocked for P3-P4 Work |
Stressing and Grouting 1st Stage |
Completed |
|
Concreting of Slab |
Completed |
|
Approval of GAD by railways(Railways Portion) |
Approved |
Approved on 1.5.2010 |
Preparation of Design and Drawing |
Inprogress |
|
Box culvert Works(Under Pass)-Raft Concreting |
Completed |
|