Prevoius Weekly Reports

   weekly progress 8.7.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 07-7-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE SHORNUR  SIDE 9 9       Completed    
2 PILE M.C SIDE 36 36       Completed      
3 PILE CAP SHORNUR SIDE 3 3       Completed      
4 PILE CAP  M.C SIDE 12 12       Completed      
5 PIER SHORNUR  SIDE 3 3       Completed      
6 PIER M.C SIDE 12 12       Completed      
7 PIER CAP SHORNUR  SIDE 3 3       Completed      
8 PIER CAP M.C SIDE 12 12       Completed      
9 RE/R WALL SHORNUR SIDE 100% 33 67% 0 10.00% 4.00% 24.00% 10.00% 25 days
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 25 days
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 1 10 days
12 BEAM/SLAB M.C SIDE 12 6 6 0 1 1 5 1 62 days
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 0 days
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 2.00% 0.00% 0.00% 2.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Deck Slab                  
17 Utility shifting                  
                     
                     
                     
  Availbility of Men                   
  Date 2/7/2011 3/7/2011 4/7/2011 5/7/2011   6/7/2011 7/7/2011    
  Nof labours 44 44 44 50   50 55    
                     
  Material Stocking Status                  
    Required Available Remarks            
  Fine aggregate {cft} 650 690              
  Cement(bag) 100 400              
  Steel inT 11 12 steel stock will be replendished soon            
  Coarse Aggreagate (cft) 430 520              
                     
  Utility shifting                  
  Utilities to be shifted   Remarks              
  BSNL COMPLETED                
  KSEB COMPLETED                
  KWA COMPLETED                
  Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date       IS 145 upto today today
 
Back
 
    
STAGING WORK OF SPAN P1-P2 07.07.2011

    
    
CLEANING OF DECK SLABS FOR HANDRAIL WORK, KERB ETC 02.07.2011

    
    
HANDRAIL POSTS REINFORCEMENT AND SLAB REINFORCEMENT OF SPAN AP1-P1 07.07.2011

    
    
PEDESTAL REINFORCEMENT OF P2 LOCATION 06.07.2011

    
 
    
SLAB BOTTOM SHUTTERING OF SPAN AP1-P1 05.07.2011

    
    
SLAB CONSTRUCTION OF SPAN P8-P9 02.07.2011

      
 

 

 

 

 

 

 

 