ROB at Athani
Work Planned upto 01.05.2010 |
Completed/Progress
|
Remarks |
RE wall works Medical College side |
In progress |
Restarted on 12.4.10 |
Fixing of panels |
Completed |
Delay due to shortage of earth for filling |
Filling |
In progress |
|
Shornur side |
|
|
Hand rail for RE wall |
In progress |
|
Drain excavation |
Completed |
|
RCC work for drain |
In progress |
|
|