   weekly progress 8.7.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 8.7.2011   
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 22 4        nil 0 0 0 2  Heavy rain obstructed the wok
2 Pile towards Puliyanam side 18 1 17        nil 2 1 1 2  

 

Date 2.7.2011 3.07.11 4.07.11 05.07.11 06.07.11 07.07.11 08.07.11
Climate sunny rainy rainy rainy rainy moody pleasant
No.of labours 42 42 42 35 35 39 40 

 

availability of material    
materials Required Available
Fine aggregate(M3) 5.66 14
Coarse aggregate(M3) 22.66 45
Cement(BAG) 200 480
Steel(TONN) 5 35 
 
Back
 
    
BORING FOR PILE AT P3(6.7.2011)

    
    
BORING AT PILE AT P3(6.7.2011)

    
    
PILE CHIPPING AT A2 (7.7.2011)

    
    
BORING AT P 6 LOCATION(6.7.2011)

    
 
    
PILE CHIPPING AT A2 (5.7.2011).

    
    
BORING FOR PILE AT P3(5.7.2011)

    
    
PILE P9 D CONCRETING(2.7.2011)

    
 
 
 

 

 

 

 

 

 

 

Untitled Document