Revised Progress Report For Mulankunnathukavu ROB for the week ending on 01-7-2011 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
|
|
|
Completed |
|
|
|
2 |
PILE M.C SIDE |
36 |
36 |
|
|
|
Completed |
|
|
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
6 |
PIER M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
9 |
RE/R WALL SHORNUR SIDE |
100% |
32 |
68% |
0 |
10.00% |
1.00% |
24.00% |
10.00% |
32 days |
shuttering work for the balance portion of retaining wall in progress. |
10 |
RE/R WALL M.C SIDE |
100% |
9 |
91% |
0 |
0.00% |
0.00% |
2.00% |
0.00% |
32 days |
|
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
0 |
3 |
0 |
0 |
0 |
0 |
1 |
17 days |
Beam reinforcement work completed for span AP1-P1 ,and shuttering works for the beam in progress |
12 |
BEAM/SLAB M.C SIDE |
12 |
6 |
6 |
0 |
1 |
0(but 1 girder complete) |
5 |
1 |
69 days |
girder concreting of the span P8-P9 completed. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
0 days |
|
14 |
HR/FP/KERB M.C SIDE |
100% |
9 |
91% |
0 |
1.00% |
1.00% |
0.00% |
2.00% |
|
.Total number of handrails casted is 90 |
15 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
25-6-2011 |
26-6-2011 |
27-6-2011 |
28-6-2011 |
|
29-6-2011 |
30-6-2011 |
1/7/2011 |
|
|
|
Nof labours |
44 |
44 |
44 |
50 |
|
43 |
45 |
45 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
|
|
|
|
|
|
|
|
|
|
|
|
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Fine aggregate {cft} |
650 |
690 |
|
|
|
|
|
|
|
|
|
Cement(bag) |
320 |
400 |
|
|
|
|
|
|
|
|
|
Steel inT |
11 |
15 |
sufficient material available at the site |
|
|
|
|
|
|
|
|
Coarse Aggreagate (cft) |
502 |
640 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
|
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
COMPLETED |
|
|
|
|
|
|
|
|
|
|
KSEB |
COMPLETED |
|
|
|
|
|
|
|
|
|
|
KWA |
COMPLETED |
|
|
|
|
|
|
|
|
|
|
Others |
COMPLETED |
|
|
TOTAL NUMBER OF HANDRAILS CASTED IS 76 upto this date |
|
|
|
IS 9 0 upto |
today |
|