Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886820
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress 1.7.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 01-7-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 32 68% 0 10.00% 1.00% 24.00% 10.00% 32 days shuttering work for the balance portion of retaining wall in progress.
10 RE/R WALL M.C SIDE 100% 9 91% 0 0.00% 0.00% 2.00% 0.00% 32 days  
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 1 17 days Beam reinforcement work completed for span AP1-P1 ,and shuttering works for the beam in progress
12 BEAM/SLAB M.C SIDE 12 6 6 0 1 0(but 1 girder complete) 5 1 69 days girder concreting of the span P8-P9 completed.
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 0 days  
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 1.00% 1.00% 0.00% 2.00%   .Total number of handrails casted is 90
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 25-6-2011 26-6-2011 27-6-2011 28-6-2011   29-6-2011 30-6-2011 1/7/2011    
  Nof labours 44 44 44 50   43 45 45    
                       
  Material Stocking Status                    
    Required Available Remarks              
  Fine aggregate {cft} 650 690                
  Cement(bag) 320 400                
  Steel inT 11 15 sufficient material available at the site              
  Coarse Aggreagate (cft) 502 640                
                       
  Utility shifting                    
  Utilities to be shifted   Remarks                
  BSNL COMPLETED                  
  KSEB COMPLETED                  
  KWA COMPLETED                  
  Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date       IS 9 0 upto today  
 
Back
 
    
KERB REINFORCEMENT AND SLAB REINFORCEMENT IN P8-P9(29.6.2011).

    
    
BEAM REINFOCEMENT WORK AT AP1-P1(27.6.2011).

    
    
BEAM REINFORCEMENT IN SPAN AP1-P1(30.6.2011).

    
    
HANDRAIL CASTING(29.6.2011

    
 
    
CROSS BEAM REINFORCEMENT IN P8-P9(25.6.2011).

    
    
BOTTOM SHUTTER SETTING AT AP1-AP1(25.6.2011)

    
    
REINFOCEMENT WORK AT AP1-P1(27.6.2011).

    
 
 
 

 

 

 

 

 

 

 

Untitled Document