Progress Report For Ponnurunni ROB for the week ending on 1.7.2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto 30.06.11 |
Balance work up to 30.06.11 |
Cumulative delay in Qty up to 30.06.11 |
Work planned during the week |
Actual work done during the week |
delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE Palarivattom side(Approach portion) |
31 |
28 |
3 |
0 |
0 |
0 |
0 |
0 |
|
kwa line to be shifted |
2 |
PILE Palarivattom side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
|
|
3 |
PILE vytilla side(Approach portion) |
42 |
0 |
42 |
0 |
0 |
0 |
0 |
0 |
|
|
4 |
PILE vytilla side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
|
|
5 |
PILE CAP Palarivattom side(Approach portion) |
8 |
5 |
3 |
2 |
2 |
2 |
0 |
2 |
|
|
6 |
PILE CAP Palarivattomside(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
7 |
PILE CAP vytilla side(Approach portion) |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
|
|
8 |
PILE CAP vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
9 |
RE WALL PANEL |
370 |
149 |
221 |
0 |
42 |
35 |
7 |
42 |
40 |
|