   weekly progress 1.7.2011
    

 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

34

66

31

 

 

0

0

 0

.

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

 

4

Pier cap

2

1

3

40

 0

 0

 0

 0

 0

 

5

Pile (Rly)pulikakadavuside

4

 

4

0

59

 0

 0

0

 

6

Pile (Rly)Nhside

4

4

0

59

0

0

0

0

0

 

6

Piers (Rly)

 

2

2

0

50

 0

 0

 0

 0

 

3rdlift of pier P1

deshutteringwork completed

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

1O

Kerb/handrail

 

kerb(both outer and inner kerbof the span P2-P3 completed this week

 

nil

Inner kerbof span p2-p3

Inner kerbconcreting of P2-P3 completed successfully

 

 

 

 

 

12

Friction slab P2-P3

 

 

PCC completed uptoa total length of 40 metres

 

 

 

 

 

Balance work of PCC of the friction slab

 

 

 

 

Activities which cannot be completed without caution

1

Pile 10Nos

Pier -2Nos

Pier Cap-2 Nos

Deck -3slab

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

12

27

Remarks

 

Fine Aggreagate(m3)

 15

 31

 .

 

Cement(bag)

 31

 45

 

 

Steel(MT)

 6

 9

 

 

 RE blocks

 2150 available at site

 

 

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 i

 

 

 

DATE 25-06-2011 27-6-2011 28-6-2011 29-6-2011 30-6-2011 1/7/2011
Weather  Rainy Heavy rain sunny   cloudy rainy Cloudy
No of days remaining 14 14 16 15 15 16
 
Back
 
    
PIER P1 3RD LIFT AFTER DESHUTTERING

    
    
PREPARATION FOR LAYING OF PCC FOR FRICTION SLAB AT N.H SIDE(28.6.2011).

    
    
COPING FOR RE BLOCKS CONCRETING FOR APPROACH PORTION(27.6.2011).

    
    
SHUTTERING WORKS FOR RE BLOCKS CONCRETING A THE N.H APPROACH PORTION(29.6.2011).

    
 
    
INNER KERB SHUTTERING WORK FOR P2-P3(25.6.2011).

    
    
INNER KERB OF P2-P3 AFTER DESHUTTERING(27.6.2011)

    
    
INNER KERB SHUTTERING WORK FOR P2-P3(25.6.2011)

    
 
 
 

 

 

 

 

 

 

 