Progress Report For Pulianam ROB for the week ending on 24.6.2011 |
Sl No |
ActivityA Description |
Total Quantity |
Cumulative progress upto 30.6.2011 |
Balance work up to 30.6.2011 |
Cumulative delay in Qty up to 30.6.2011 |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
Pile towards NH side |
26 |
21 |
5 |
nil |
3 |
3 |
0 |
3 |
|
2 |
Pile towards Puliyanam side |
18 |
0 |
0 |
nil |
0 |
0 |
0 |
0 |
|
Status of utility shifting
SlNo |
Utilities |
Activities |
Date |
Status |
Remarks |
1 |
KWA |
Joint Inspection with AE,KWA,Angamali |
17.3.2011 |
DD submitted |
shifting completed |
2 |
BSNL |
Joint Inspection with DE, BSNL,Angamali |
17.3.2011 |
Estimate to be received |
Shifting completed |
3 |
KSEB |
Joint Inspection with Sub Engineer, KSEB,Karukutti |
23.3.2011 |
DD submitted |
Shifting completed |
4 |
|
Joint Inspection with AE,KSEB,Angamali |
8.4.2011 |
DD submitted |
Shifting completed |
5 |
KWA |
Joint Inspection with AE,Project division,KWA,Aluva |
8.4.2011 |
DD submitted |
shifting completed |
|