Untitled Document
Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
8053283
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Prevoius Weekly Reports
Weekly Progress Report as on 01/07/11
Tota 17 piles completed
2 piles completed in this week
Back
BORING AT P15-A (25.06.2011)
BORING AT P15A (25.06.2011)
REINFORCEMENT ERECTION ON P15 A (25.07.2011)
SPT CHECKING ON P13 (27.06.2011)
CONCRETING ON P13C (28.07.2011)
DEMOLISHING BUILDING AT PADANNA SIDE (30.07.2011)