|
ROB at Athani
Work Planned upto 08.05.2010 |
Completed/Progress |
Remarks
|
RE wall works Medical College side |
In progress |
Restarted on 12.4.10 |
Fixing of panels |
Completed |
Delay due to shortage of earth for filling |
Filling |
Completed |
|
PCC for friction slab |
In progress |
|
Shornur side |
|
|
Sectioning for road work |
In progress |
|
Hand rail for RE wall |
In progress |
|
Drain excavation |
Completed |
|
RCC work for drain |
In progress |
|
|