Prevoius Weekly Reports
|
28-11-2009 |
|
Work Planned upto 28/11/2009 |
Completed/Progress |
Delay |
Handrail & Footpath slab |
Completed
|
|
RE wall works Medical College side -delay by contractor |
Not started |
30 days delay by the contractor - |
|
|
Medical College side |
|
|
not started |
Retaining wall on Shornur side |
In progress |
|
|
|
Back |
|
No images are uploaded for this Weekly Reports
|
|
|