Work Planned upto 27-02-2010 |
Completed/Progress |
Delay |
Retaining wall excavation |
One side completed |
Road to be closed for balance |
|
|
portion of retaining wall work. |
|
|
No work front available for further works |
Retaining wall concreting - one side |
Completed |
|
Lifting work - three spans (Malampuzha side) |
Completed |
|
Lifting work -4th span (Palakkad side) |
In progress |
|