Prevoius Weekly Reports
|
27/03/2010 |
|
Work Planned upto 27.03.2010 |
Completed/Progress |
Delay |
Filling earth inside retaining wall |
In progress |
|
Balance portion concreting wall upto kerb |
Completed |
|
Reinforcement work for kerb |
In progress |
|
Lifting work -5 spans |
Completed |
|
|
|
Back |
|