Graph Project Graph

Progress report of Divine Nagar ROB-19.09.15
 

Weekly Progress of Adjacent span of Divine Nagar ROB as on 19.09.15

Sl. No:

Particulars

Status

Remarks

1

Slab RP1-P6A ADJACENT SPAN

Completed

 

2

Slab RP2-P7 ADJACENT SPAN

 Completed

 

3

Handrail and kerb

In progress

Kerb completed. Handrail balance at expansion joint area

4

Expansion joint

Completed

 

5

Wearing coat

In progress

 Divine side completed

6

Painting works

In progress

 80% completed

7

Stair case work

In Progress

Footing completed on Divine side. Columns reached up to EGL

 
Click here to view Previous Reports
 
    
RAILWAY PORTION WORKS

    
    
KADUKUTTY SIDE EXCAVATION FOR STAIRCASE

    
    
PAINTING RP1-P6A SPAN.

    
    
RAILWAY SPAN WORK IN PROGRESS.

    
    
DIVINE SIDE OF ROB.

    
    
PAINTING WORK IN RP2-P7 SPAN

      
 

 

 

 

 

 

 

 