Project Graph
Weekly Progress of Adjacent span of Divine Nagar ROB as on 19.09.15
Sl. No:
Particulars
Status
Remarks
1
Slab RP1-P6A ADJACENT SPAN
Completed
2
Slab RP2-P7 ADJACENT SPAN
3
Handrail and kerb
In progress
Kerb completed. Handrail balance at expansion joint area
4
Expansion joint
5
Wearing coat
Divine side completed
6
Painting works
80% completed
7
Stair case work
In Progress
Footing completed on Divine side. Columns reached up to EGL