ROB at Athani
Work Planned upto 29.05.2010 |
Completed/Progress |
Remarks |
RE wall works Medical College side |
Completed |
Restarted on 12.4.10 |
PCC for friction slab |
Completed |
|
Friction slab concreting |
In progress |
|
Hand rail for RE wall |
In progress |
|
Approach slab concrecting |
Completed |
|
WBM Work 3rd Layer |
In progress |
|
Applicaton of Mastic Asphalt |
Completed |
|
Drain Works |
Completed |
|
|