Work Planned upto 15.05.2010 |
Complted/Progress |
|
Toll booth plastering |
In progress |
|
Hand rail fixing |
In progress |
|
Filling earth inside retaining wall |
Completed |
|
Retaining wall upto kerb |
Completed |
|
Reinforcement work for kerb, Approach slab & concreting |
Completed |
|
Lifting work of spans |
Completed |
|
Supply of aggregates for WBM |
In progress |
|