Prevoius Weekly Reports
|
08-05-2010 |
| |
Details of work done upto 08-05-2010
|
Filling earth inside retaining wall |
Completed |
|
Retaining wall upto kerb |
Completed |
|
Reinforcement work for kerb, Approach slab & concreting |
Completed |
|
Lifting work of spans |
Completed |
|
Handrails work |
In progress |
|
| |