   06-03-2010
     Details of work done done upto 06-03-2010

Work Planned upto 06.03.2010
Completed/Progress Delay
Retaining wall excavation One side completed  
Balance portion Pcc Completed Road closed for balance
Bar bending for balance portion In progress portion of retaining  wall work.
Retaining wall concreting - one side Completed  
Lifting work - three spans (Malampuzha side) Completed  
Lifting work  -2 spans (Palakkad side) In progress  
 