Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886750
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress as on 26.4.2011
    
Revised Progress Report For Mulankunnathukavu ROB for the week ending on 24-06-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE SHORNUR  SIDE 9 9       Completed    
2 PILE M.C SIDE 36 36       Completed      
3 PILE CAP SHORNUR SIDE 3 3       Completed      
4 PILE CAP  M.C SIDE 12 12       Completed      
5 PIER SHORNUR  SIDE 3 3       Completed      
6 PIER M.C SIDE 12 12       Completed      
7 PIER CAP SHORNUR  SIDE 3 3       Completed      
8 PIER CAP M.C SIDE 12 12       Completed      
9 RE/R WALL SHORNUR SIDE 100% 29 71% 0 15.00% 3.00% 15.00% 10.00% 39 days
10 RE/R WALL M.C SIDE 100% 9 91% 0 2.00% 0.00% 2.00% 0.00% 39 days
11 BEAM/SLAB SHORNUR  SIDE 3 0 3 0 0 0 0 0* 24 days
12 BEAM/SLAB M.C SIDE 12 6 6 0 1 0 4 1 76 days
13 HR/FP/KERB SHORNUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 4 days
14 HR/FP/KERB M.C SIDE 100% 9 91% 0 1.00% 1.00% 0.00% 2.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Deck Slab                  
17 Utility shifting                  
                     
                     
                     
  Availbility of Men                   
  Date 18-6-2011 19-6-2011 20-6-2011 21-6-2011   22-6-2011 23-6-2011 24-6-2011  
  Nof labours 40 35 43 45   43 48 44  
                     
  Material Stocking Status                  
    Required Available Remarks            
  Fine aggregate {cft} 800 770              
  Cement(bag) 630 830              
  Steel inT 11 20 sufficient material available at the site            
  Coarse Aggreagate (cft) 780 820              
                     
  Utility shifting                  
  Utilities to be shifted   Remarks              
  BSNL COMPLETED                
  KSEB COMPLETED                
  KWA COMPLETED                
  Others COMPLETED     TOTAL NUMBER OF HANDRAILS CASTED IS  76 upto this date          
 
Back
 
    
REINFORCEMENT OF RC WALL IN THE APPROACH PORTION

    
    
DESHUTTERING OF P7-P8 SPAN

    
    
LIFTING OF SLAB AND BEAM SHUTTERING

    
    
HAND RAIL CASTING

    
 
    
SHUTTERING WORK FOR RCC WALL

      
 

 

 

 

 

 

 

 

Untitled Document