Si No
Activity Description
Total Quantity
Cumulative progress uptolast week
Balance work up to last week
Cumulative delay in Qty up to this week
Work planned during the week
Actual work done during the week
Work Planned for next week
Remarks
1
RE/R WALL PALAKKAD SIDE
100%
62%
38%
0
2.00%
2
RE/R WALL MOYAN SCHOOL SIDE
18%
82%
3.00%
3
BEAM/SLAB Staging PALAKKAD SIDE
4
BEAM/SLAB Bar bending and Fixing PALAKKAD SIDE
5
BEAM/SLAB Bar Shuttering And Concreting PALAKKAD SIDE
6
BEAM/SLAB Staging MOYAN SCHOOL SIDE
7
BEAM/SLAB Bar bending And Fixing MOYAN SCHOOL SIDE
8
BEAM/SLAB Shuttering and Concreting MOYAN SCHOOL SIDE
9
BEAM/SLAB RAILWAY SPAN
10
HR/FP/KERB CALICUT SIDE
0.00%
11
HR/FP/KERB NH SIDE
12
HR/FP/KERB RAILWAY SPAN
13
BC/PAINTING
Note: Progress review done based on the revised Program (rev-01)
ROB Sulthanpet, Palakkad
Date
Barbenders
Mechanics/Electricains
Helpers
Ret. Wall work
18-06-2011
19
17
19-06-2011
20-06-2011
21-06-2011
22-06-2011
16
23-06-2011
24-06-2011
23
Material Stocking Status
Required
Available
Fine aggregate {m³}
22
Cement(bag)
250
2250
Steel inT
135
Coarse Aggreagate (m3)
36