   28.06.2010
    

ROB at Koratty

PROGRESS OF ROB WORK AS ON 26.06.2010

 

Work Planned upto 26-6-2010 Completed/ Progress Remarks
P3-P4 Span   Road Blocked for P3-P4 span work.
Preparation for final stressing In progress  
Concreting of Slab Completed  
Approval of GAD by railways (Railway Portion) Approved Approved on 1-5-10
Preparation of Design and Drawing In progress  
Under Pass Wall concreting 3rd lift In progress  
 