   Weekly Progress report as on 24/06/2011
    

12 piles completed

 
Back
 
    
TRIPOD SETTING AT P 13 (23/06/2011)

    
    
TRIPOD SETTING (23/06/2011)

    
    
PILE CONCRETING IN PROGRESS (22/06/2011)

    
    
PILING IN PROGRESS P8 (24/06/2011)

    
 
    
PILING IN PROGRESS (22/06/2011)

      
 

 

 

 

 

 

 

 